1060 施工进展及买家贷款通知

2018年08月31日 墨尔本地产在线



近期我们会通知打算做贷款的买家准备贷款文件,请关注通知!

有任何相关问题请联系项目主管 Jason 0424 166 888



JUNE 2018 (2018年六月)

This month was a milestone for the project as all demolition and excavation works have been completed.  The builders have cleared the land to start construction on the two basement levels for parking. 
本月是1060项目的里程碑因为我们已完成所有拆除和挖掘工程。施工人员已清理了地面并开始建造两层地下车库。



Above: Bulk excavation works 上方图片:大型挖掘工程


JULY 2018 (2018年7月)

Completed items since construction 施工后已完成项目

Marking our 6 month of construction on 1060, we have now erected the tower crane that will allow the builders to start building the 10 levels of this project! In case you don't know, this project will be the highest building in the Carnegie area; allowing residents on upper levels to have unobstructed views of the city skyline and even see the Dandenong Ranges!

1060项目施工六个月以来,我们现在已经建造了塔式起重机,这将使建筑师能够开始建造这个项目的10层!如果你不知道,这个项目将是卡内基地区最高的建筑物;让上层居民可以享有一览无余的城市天际线,甚至可以看到丹德农山脉!



Our project is strategically located less than 5 minutes walk to Carnegie Station. In relation to that, the station is being revamped to keep up with the modern era. The railway has been elevated to allow smoother traffic flow.

我们的项目地理位置优越,步行不到5分钟即可到达卡内基火车站。与此相关的是,该站正在进行改造以跟上现代时代的步伐。铁路已经升高以允许更顺畅的交通流量。


我们将会继续更新1060 Carnegie 项目施工进展,敬请期待。





收藏 已赞